The column mounted hydraulic rotary drilling rig has the characteristics of low price, reasonable structure, strong power, flexible operation, small footprint, strong adaptability, light weight, fast relocation, high efficiency, reliable fixation, and convenient maintenance and separation, and is deeply loved by mining workers.
Based on feedback from mining workers and our company's after-sales service team's problem-solving records, we have summarized the key points of daily use and maintenance of the drilling rig. Mastering these points will make your drilling rig more durable and have a longer lifespan.
1. Before installing the drilling rig and erecting the column, the top plane of the column should be as parallel as possible to the bottom surface; Clean the bottom to ensure that there are no loose debris on the bottom surface, place sleepers on top and bottom, adjust the vertical column, apply pre tightening force, and then attach the bracket part to the taper axis of the bracket seat. Tighten the large nut to fix it.
2. Before connecting the pipeline, it should be cleaned thoroughly to avoid contaminating hydraulic oil and damaging hydraulic components. Connect the water and oil pipes according to the joint markings of the drilling rig pump station to ensure they are firm, reliable, and error free.
3. Inject N46 or N68 anti-wear hydraulic oil into the oil tank of the pump station, with the oil level reaching 4/5 of the oil tank.
4. Check whether each control valve is flexible and reliable, and whether the action is consistent. Before starting, the motor and oil cylinder reversing valves should be in the middle position to avoid starting difficulties.
Everything is ready and we can work smoothly now!